Telangana’s 4,000 MW Yadadri Thermal Power Plant Set to Achieve Full Capacity in December - Maverick News30

State / 1 hr ago / Team Maverick

Telangana’s 4,000 MW Yadadri Thermal Power Plant Set to Achieve Full Capacity in December

Listen to this story
Telangana’s 4,000 MW Yadadri Thermal Power Plant Set to Achieve Full Capacity in December

Hyderabad, Nov 2026 : Telangana's 4,000 MW Yadadri Thermal Power Station is preparing to commence commercial operations of its fifth and final unit in December, paving the way for the plant to achieve its full generation capacity. Officials said the state government and Telangana Power Generation Corporation (TGGENCO) are taking measures to strengthen coal supply arrangements and resolve technical issues to ensure uninterrupted power generation.

With all five units becoming operational, the Yadadri plant is expected to play a significant role in improving Telangana's power self-sufficiency and meeting the rising electricity demand, particularly during the upcoming Rabi season.

TGGENCO is working towards achieving a generation target of 4,000 MW during the Rabi season through long-term coal procurement agreements, infrastructure improvements and modernisation of the plant's coal handling systems.

The thermal power station comprises five units, each with an installed capacity of 800 MW. Four units have already commenced commercial production, while the fifth unit was connected to the power grid on October 20. Its commercial operation is expected to begin in December.

According to officials, TGGENCO has prepared a comprehensive action plan to address technical problems in the coal supply system and ensure that all five units can operate at their full capacity.

The Yadadri project, which faced several challenges during its implementation, has now reached an important operational stage. Its progress was affected by the COVID-19 pandemic, delays in obtaining forest clearances, issues concerning railway land and directions issued by the National Green Tribunal over environmental clearances.

Following the state government's intervention, environmental impact assessment studies and public consultations were undertaken afresh, allowing construction work to resume in February 2024.

At the plant, the major power generation systems, including boilers, turbines and generators, along with ash handling and water supply infrastructure, are functioning satisfactorily. However, technical problems in the coal handling plant had affected the smooth movement and supply of coal to the generating units.

Taking serious note of the issue, the state government initiated targeted corrective measures. Following directions from Chief Minister A. Revanth Reddy and under the guidance of Deputy Chief Minister Bhatti Vikramarka, a high-level team comprising officials from Bharat Heavy Electricals Limited (BHEL) and TGGENCO, led by the Special Chief Secretary of the Energy Department, reviewed the situation at the plant.

TGGENCO Chairman and Managing Director, BHEL's Director (Power) and other senior officials conducted inspections and prepared an action plan with specific targets to resolve the operational bottlenecks.

The measures have resulted in the restoration of four coal supply lines, providing a combined coal-handling capacity of 3,200 tonnes per hour, with each line handling approximately 800 tonnes per hour. The improvement has reduced interruptions in coal supply and enhanced the plant's operational performance.

The government is also implementing a multi-pronged strategy to maintain adequate coal stocks. Arrangements have been made to transport three to four coal rakes daily from the Naini coal mine operated by Singareni Collieries Company Limited (SCCL). So far, approximately 4.26 lakh metric tonnes of coal have been transported from the mine to the Yadadri plant.

In addition, agreements were finalised on November 4 for procuring 4.6 lakh tonnes of coal from Mahanadi Coalfields Limited (MCL) and South Eastern Coalfields Limited (SECL). Transportation from these sources has already commenced.

With the fifth unit preparing for commercial production and coal supply infrastructure being strengthened, Telangana is looking to make the Yadadri Thermal Power Station a major contributor to the state's electricity requirements during the Rabi season and beyond.